Ejecución de Sentencia y valoraciones expropiatoriasel caso del cementerio de Valencia. Comentario a la STS de 23 de marzo de 2017

  1. FERNANDO GONZÁLEZ BOTIJA 1
  1. 1 Universidad Complutense de Madrid
    info

    Universidad Complutense de Madrid

    Madrid, España

    ROR 02p0gd045

Revista:
Revista de urbanismo y edificación

ISSN: 1576-9380

Any de publicació: 2017

Número: 40

Pàgines: 97-106

Tipus: Article

Altres publicacions en: Revista de urbanismo y edificación

Resum

The Supreme Court confirms in its 23rd March, 2017 ruling that the City Council of Valencia has to pay almost eight million euros to the owners of a real state of 42,916 square meters - formed by 10 plots - that was expropriated for the expansion of the General Cemetery of the city. The Supreme Court considers that the correct method of evaluating the land was applied when enforcing the judgment.