Factores de riesgo que inciden negativamente en los cumplimientos de tiempo y coste programados en la ejecución de proyectos de edificios de uso hotelero en España

  1. GarciaCasares, Rebeca
Dirigida por:
  1. Antonio Eduardo Humero Martín Director/a

Universidad de defensa: Universidad Politécnica de Madrid

Fecha de defensa: 18 de diciembre de 2015

Tribunal:
  1. Manuel José Soler Severino Presidente/a
  2. Diego Rodríguez Rodríguez Secretario
  3. Victor Herrera Medina Vocal
  4. Montserrat Castellanos Moreno Vocal
  5. Antonella Sassano Vocal

Tipo: Tesis

Resumen

Cost and schedule overruns constitute a very frequent phenomenon in the construction industry. A large number of construction projects do not finish on the estimated time and cost, and this scenario seems to be becoming the norm rather than the exception. Construction projects are heterogeneous by nature and they can become very complex as they involve a large number of processes which are subject to many variables and factors that may give rise to time and cost overruns. Time and cost overruns cause dissatisfaction not only to owners but all stakeholders involved in the project, leading most of the times to undesirable situations of conflicts and adversarial relationships between project participants. Hence, it becomes necessary to adopt an effective risk management strategy as an essential part of project management in order to achieve project success. Construction projects may have different characteristics depending on the type of project. This research specifically focuses on hotel construction projects. Hotel projects usually involve complex organizational structures, including many project participants and processes which develop in an environment that is already dynamic by nature. In this type of projects, the achievement of time and cost objectives is particularly important, as any delay of the hotel opening date will result in significant loss of business and market share and may also involve key important implications related to hotel operations. If the risk factors that lead to time and cost overrun are known in advance, preventive actions could be established in order to avoid them, so that time and cost overruns are minimized. This constitutes the aim of this research, being risk identification the first step of any effective risk management strategy for project success. The context of this research is focused on a particular geographical area, Spain. Tourism in Spain is a major contributor to the Spanish economy, and efficiency and competiveness should also be reflected in the building processes of the hotel industry, where delays and cost overruns should be kept to the minimum. The aim of this study is to explore the most critical risk factors leading to time and cost overruns in hotel construction projects in Spain. From the analysis of the literature review, a proposal of a risk identification framework is developed, which will be further analyzed by a qualitative assessment based on expert opinions and the study of specific case studies. From the results of this assessment, the levels of risk criticality are determined for the identified factors, a comparison of the perceptions of risk levels among different groups of respondents is also carried out, and a procedure for prioritization of factors in terms of needs of response is established. A final proposal of a risk register matrix framework is then developed in order to assist hotel owners, project management companies or other hotel project stakeholders, and provide them with a base to design their own specific risk management plans, contributing in this way to project success with regards to the achievement of cost and time objectives.